Mountain View Elementary School was constructed in 1959 and is in need of a new facility required to meet modern educational standards.

With multiple portable classrooms, a small combined gym and cafeteria and limited space for learning and parent conferences, Mountain View ranked as the 8th worst elementary school for Educational Adequacy in the 2016 Facilities Audit.  

A new school, in the same location, will meet modern education standards, and provide additional space for physical education and music.

July 3, 2019: The LKV designed Mountain View Elementary project managed by Kreizenbeck Constructors is underway. Site prep and construction of the building pad continues. Concrete footings and stem walls are approximately 50% complete. Under slab utility rough-ins are in progress. Construction of masonry walls are in progress. The new building is scheduled to be completed for the start of the 2020-2021 School Year.