Hillside Junior High - Update

Built in 1960 and intended for temporary use, Hillside Junior High is out-of-date and overcrowded. Particularly the gymnasium, the cafeteria and performing art spaces.  

 

Ranking last among junior high schools on all three major 2016 Facilities Audit categories (Utilization, Educational Adequacy and the Facilities Condition Index), the addition of a new gym, as well as the expansion of the cafeteria and performing arts classrooms, will bring Hillside up to safe, modern standards.

July 3, 2019: Russell Corporation reports final inspections of the Gymnasium/cafeteria is scheduled for July 9. Abatement is in progress in the old cafeteria/Kitchen and framing for the new classrooms is underway. HVAC ductwork is being installed and plumbing rough-in is in progress. Substantial completion is scheduled for September 2019.