Boise High - Update



Work began during the summer of 2017 to renovate Boise High School's old gymnasium, which was built in 1936 and now serves primarily as a space for physical education classes.  The renovation project also includes rebuilding the music building to better serve students by the addition and improvement of performing arts classrooms. This bond capital project was completed and dedicated on Friday, May 10, 2019 and brings one of Boise High’s oldest building up to safe, modern standards.  


May 10, 2019 Update:   A dedication/ribbon cutting ceremony for the newly renovated 1936 Gymnasium and Performing Arts Addition was held on Friday, May 10, 2019 from 2 p.m. to 3 p.m. with public tours from 3 p.m. to 4 p.m. 

June 5, 2019 Update:  CM Company reports epoxy coatings in the locker rooms are complete and lockers are installed. The gym curtain is currently being installed. Miscellaneous finish tasks are being completed and cleaning activities are in progress. The project was designed by Hutchison Smith Architects.

.