June 5, 2019 Update:  Perkins Construction has completed installation of all finishes including TEKTUM ceiling and wall panels, lighting fixtures and other sports equipment in the Gymnasium. The main electrical panels are currently being replaced. Paint and floor covering installation is underway in the classroom wing and are expected to be complete June 14. Exterior finishes are being installed, concrete sidewalks are being formed and placed, and completion of the asphalt playground is planned by June 21. We continue to work with the Contractor to
accelerate the schedule.