Collister Elementary - Update

Built in 1912, Collister is overcrowded and outdated. With multiple portable classrooms and one of the District’s smallest combined cafeteria-gym-auditorium, Collister ranked in the bottom third on all three major 2016 Facilities Audit categories (Utilization, Educational Adequacy and the Facilities Condition Index).


A completely remodeled and expanded school will help meet modern education standards while preserving an historic neighborhood school.


February 8,  2023 Update: The Collister addition/remodel is being designed by LKV Architects and managed by Beniton Construction.  Bids will be opened on February 23, 2023. Construction will start summer of 2023.

March 8, 2023 Update:  The Collister addition/remodel is being designed by LKV Architects and managed by Beniton Construction. Bids will be opened on March 7, 2023. Construction will start summer of 2023. 

March 10, 2023 Update: Review letter to Collister Elementary families, staff and neighbors

 

June 7, 2023 Update: The project was designed by LKV Architects and is managed by Beniton Construction. Demo and construction activities are underway and will be completed in August 2024.

July 5, 2023: The project was designed by LKV Architects and is managed by Beniton Construction. Demo and construction activities are underway and will be completed in August 2024.

September 6, 2023: The project was designed by LKV Architects and is managed by Beniton Construction. Gym and elevator footings and foundation walls are complete. Mason will mobilize and begin wall construction next week. Structural remediation work has begun in the existing building. Construction will be completed in August 2024 

January 4, 2024: The project was designed by LKV Architects and is managed by Beniton Construction. Structural masonry walls are approximately 80% complete. Stair core and elevator shaft is being constructed. Slab on grade concrete is 100% done. Second floor structural framing and decking is scheduled for later this month. Construction will be completed in August 2024.

February 12, 2024: The project was designed by LKV Architects and is managed by Beniton Construction. Brick veneer is in progress. Second floor structural framing and decking has begun.
Construction will be completed in August 2024.

March 11, 2024: The project was designed by LKV Architects and is managed by Beniton Construction. The brick veneer is in progress. Mechanical/Plumbing/Electrical rough ins are also in
progress. Cafeteria membrane roofing is being installed. Construction will be completed in August 2024.

April 8, 2024: The project was designed by LKV Architects and is managed by Beniton Construction. Exterior windows are currently being installed in the building. Two dead trees have been
removed out front. Rough-in plumbing and gypsum board are complete in the new building. Millwork is currently being installed in the old section. The project
will be completed prior to the 2024/2025 school year.

May 8, 2024: The project was designed by LKV Architects and is managed by Beniton Construction. Exterior windows are currently being installed in the building. Two dead trees have been
removed out front. Rough-in plumbing and gypsum board are complete in the new building. Millwork is currently being installed in the old section. The project
will be completed prior to the 2024/2025 school year.

June 5, 2024: The project was designed by LKV Architects and is managed by Beniton Construction. Currently, glass is being placed, concrete work is underway, and the gym floor is currently being installed. The project will be completed before the 2024/2025 school year.